← Engineering Services

101714 — Outer Loop West, Phase I (Tarver Drive to Riverside Trail) {TXDOT Grant}

Stageactive
CategoryMultiple Types
CIP Program—
Managing DepartmentEngineering Services
Benefiting Department—
Project ManagerEd Kolacki
StatusComplete
Scheduled Completion2026-03-01
Planned Start FY—
Planned Completion FY—
Budget$33,214,722
Actual / Committed$32,998,007